(Added short user manual) |
kGeen bewerkingssamenvatting |
||
Regel 16: | Regel 16: | ||
The dialog of advanced closures is opened by clicking on the button on the closure tab of a segment. There are two section of the dialog. | The dialog of advanced closures is opened by clicking on the button on the closure tab of a segment. There are two section of the dialog. | ||
==== Top section ==== | ====Top section==== | ||
[[File:AC1.png|alt=Advanced Closures - Top Section|right|frameless|400x400px|Advanced Closures - Top Section]] | [[File:AC1.png|alt=Advanced Closures - Top Section|right|frameless|400x400px|Advanced Closures - Top Section]]'''1. Range''' | ||
Range of two dates between the closure(s) should be applied. | Range of two dates between the closure(s) should be applied. | ||
'''2. Start''' | |||
Start time of the closure in hh:mm | Start time of the closure in hh:mm | ||
'''3. Duration''' | |||
Duration of the closure. Top field is days, bottom field is hours. | Duration of the closure. Top field is days, bottom field is hours. | ||
'''4. Other properties of the closure''' | |||
==== Bottom Section ==== | ====Bottom Section==== | ||
{| class="wikitable" | {| class="wikitable" | ||
|'''Repeat''' | |'''Repeat''' | ||
Regel 51: | Regel 51: | ||
|'''Preview''' | |'''Preview''' | ||
The preview shows the closures the will be put on a selected segment when you click apply. It allows you to verify data has been entered correctly and that the closures will appear as intended. An orange exclamation mark icon will appear at the end of each line if there’s an issue. You can see what the issue is by hoovering over the icon with your cursor. After you click apply, a green “OK” will appear for closures successfully added. | The preview shows the closures the will be put on a selected segment when you click apply. It allows you to verify data has been entered correctly and that the closures will appear as intended. An orange exclamation mark icon will appear at the end of each line if there’s an issue. You can see what the issue is by hoovering over the icon with your cursor. After you click apply, a green “OK” will appear for closures successfully added. | ||
| | |[[File:AC5.png|alt=Advanced Closures - Preview|frameless]] | ||
|} | |} | ||
Note that if you add more than a handful of closures, it will take a good few minutes to process this. Meanwhile some closures may show in a single direction only, also when they have been entered as dual direction closures. Please wait and refresh the view to check whether all goes well. | Note that if you add more than a handful of closures, it will take a good few minutes to process this. Meanwhile some closures may show in a single direction only, also when they have been entered as dual direction closures. Please wait and refresh the view to check whether all goes well. |
Versie van 13 mei 2020 15:31
WME Advanced Closures
Waze Map Editor (WME) script that handles recurrent and imported closures.
Below follows a synopsis of the explanation on how to use the script located on the forum thread's first page, as it is not particularly straight forward to use.
The dialog of advanced closures is opened by clicking on the button on the closure tab of a segment. There are two section of the dialog.
Top section
1. Range
Range of two dates between the closure(s) should be applied.
2. Start
Start time of the closure in hh:mm
3. Duration
Duration of the closure. Top field is days, bottom field is hours.
4. Other properties of the closure
Bottom Section
Note that if you add more than a handful of closures, it will take a good few minutes to process this. Meanwhile some closures may show in a single direction only, also when they have been entered as dual direction closures. Please wait and refresh the view to check whether all goes well.
Pro-tip: adding a lot of closures to multiple segments is not always working great. If at all possible, it’s better to apply multiple closures to one segment at the time.